Grays New Drainage

Works Description:

Drainage                                                                                                

Duration:

3 Weeks

Contract Value:

£25,000 > £50,000

Client:

Waco UK Ltd

          

The drainage works DB Construction carried out on behalf of Waco UK Ltd involved live sewer connections. Our experienced gang connected a tempory accommodation block to the main sewer, and the surface water drainage system to the surface water outlet.

DB Construction excavated fifteen meters of trench up to a depth of 2.5 meters to enable the foul drain run to be picked up from the building and be connected to the public sewer, 150mm diameter super sleeve pipe was installed along with 2 new inspection chamber consisting of 1.2 meter diameter chambers.

 As with all deep drainage meticulous planning and experience is vital due to the potential dangers involved with these works. The work was completed on time, safely and to a high standard.