West Road, Clacton
Works Description: |
Kerbs, Edgings, New Highway Construction, Drainage, Asphalting |
Duration: |
5 Weeks |
Contract Value: |
£25,000 > £50,000 |
Client: |
Ringway / Essex County Council |
Key Works: Kerbs, Edgings, New Highway Construction, and Asphalting.
West Road works package required 100’s of meters of new asphalt finished footpath of 1.5m width to be constructed in the existing grass verge incorporating a new bus lay-by. Works were carried out under normal working hours so as to ensure we impacted on our environment and the residents as little as possible and allowing traffic to run as normal.
DB Construction used innovative Rocksaw Trenching equipment to excavate 100m’s of existing carriageway for the new kerbline. The work was carried out fast and efficiently in a matter of hours at a fraction of the cost of Diamond Sawing, and where conventional methods would have taken days. With a water suppression kit fitted dust was kept to a minimum.
This total works was made up of:
- 100’s of meters of kerb and footpath edgings,
- Kasel kerb construction in the new bus lay-by,
- New highway construction &
- New footpath construction including 700m2 of asphalting.
All works were completed in just a few weeks.
Our Accreditations

We are fully accredited to illustrate our commitment to the construction industry, quality assurance, safety & health standards and environmental awareness. More…
J's Hospice

The J's Hospice is an incredible charity which DB Construction have made a company long pledge to support. Find out More....
KPI's

Having delivered hundreds of diverse schemes in 2010-2011 we measured the quality of delivery for every project and are proud of our performance. See how we scored for yourself. More…
Carbon Neutral

As a sign of our commitment to the environment DB Construction in conjunction with Carbon Earth will be presenting each of our clients who would like them with tree planting certificates, on successful project completion. The certificate shows exactly how DB Construction has off set the carbon emissions generated on the project on behalf of our client, including what type of trees have been planted and their exact GPS location. More......